- All guides
- Certification timeline: the durations set by the texts
Certification timeline: the durations set by the texts
Most certification timelines published online, this page's own earlier version included, are tables of "6 to 8 weeks" and "8 to 10 months" with no source behind them. This rewrite keeps only durations that a text actually fixes: a regulation, a regulator's published service standard, or the scheme owner's own process document. Those clocks are fewer than people expect, and most of them start only once a complete file is filed. Testing in an ISO/IEC 17025 lab, sample logistics, retests and translation sit outside every one of them. The rest of your schedule has to come from your own lab, TCB and notified body quotes, and this page says where those gaps are.
How to read a regulatory clock
Section titled “How to read a regulatory clock”Three questions decide whether a duration in a text helps your plan:
- When does the clock start? Almost always at a complete application, not at the start of testing. Korea, China and ISED all say so explicitly, and China excludes testing time from its 15 working days.
- Who is bound? Some clocks bind the authority (Korea, China, Peru), some only state a target (ISED service standards), and some bind you (FCC Grantee Code fee, PTCRB TAC reservation).
- What does it cover? A 5-day certification in Korea excludes the time spent verifying the test report; T-Mobile five business days applies only "if you meet all of T-Mobile requirements and there are no certification issues".
Durations fixed by a text, regime by regime
Section titled “Durations fixed by a text, regime by regime”| Regime | Step | Duration | When the clock starts, what it excludes | Source |
|---|---|---|---|---|
| FCC | Grantee Code fee | 30 days | From issuance of the code; unpaid code is removed and a new one must be obtained | 47 CFR 2.926(c) |
| FCC | TCB review of a certification | None | No rule sets a review time; TCB fees are set by each TCB (2.962(e)) | 47 CFR 2.962 |
| FCC | PAG review (listed equipment only) | "Typically 2 to 6 weeks" | A description in the order, not a rule; since June 15, 2026 the PAG list prioritizes equipment tested in Trusted Test Labs (2.964(a)) | FCC 26-28, para. 65 |
| FCC | Set-aside of a grant | 30 days | From the date of grant; the TCB or the FCC may set aside a non-compliant grant, after which only the FCC can revoke it under 2.939 | 47 CFR 2.962(f) |
| FCC | Short-term confidentiality | 180 days at most | From the grant date | KDB 726920 |
| FCC | TCB report on corrective action after post-market surveillance | 30 days | The TCB reports the grantee actions to the Commission | 47 CFR 2.962(i)(4) |
| EU (RED, Decision 768/2008/EC) | EU-type examination by a notified body | None | Neither text sets a time limit for module B | RED Annex III |
| EU (RED) | Keeping technical documentation and EU DoC | 10 years | After the radio equipment is placed on the market | RED Article 10(4) |
| EU (Decision 768/2008/EC) | Start of a newly notified body | 2 weeks or 2 months | Objection window after notification, with or without accreditation | Article R23(5) |
| EU (MDR) | Designation of a medical device notified body | 28 days | Objection window for Member States and the Commission | MDR Article 42(6) |
| EU (CRA) | Reporting an actively exploited vulnerability | 24 hours, 72 hours, 14 days | Early warning, notification, then final report within 14 days after a corrective measure is available; applies from September 11, 2026 | CRA Articles 14(2) and 71 |
| Canada (ISED) | Wireless equipment certification by ISED | 14 calendar days | Service standard, from a complete application | ISED service standards (June 2025) |
| Canada (ISED) | Age of the test report | 12 months at most | At application | RSS-Gen section 3.4.1 |
| PTCRB | IMEI TAC reservation | 120 days | From the TAC request; revoked if the device is not certified by then | PPMD 8.6 |
| PTCRB | NAPRD03 version | Latest or previous | Version current when test reports are uploaded; four releases a year | PPMD 11.7, 5.2 |
| PTCRB | Delayed public listing | 1 to 365 days | After certification, at the manufacturer's choice | PPMD 11.3.1.12 |
| AT&T | Device with an unapproved module | PTCRB testing "can take 8-12 weeks", AT&T lab and field testing "can take 4-6 weeks" | Published by AT&T | AT&T Get Certified |
| AT&T | New eUICC through ASAP | "Approximately 8 weeks" | Published by AT&T | AT&T SIM page |
| T-Mobile | Technical Acceptance | "As little as five business days" | Only with all requirements met and no certification issues | T-Mobile process page |
| South Korea (RRA) | Registration / certification / interim certification | Immediately / 5 days / 30 days, extendable once by 15 days | From filing; time spent verifying the test report not counted for certification | RRA Notice 2026-4, Article 29 |
| China (SRRC) | Type approval decision | 15 working days | From acceptance; testing, organized by the radio administration, not counted | MIIT Order 57, Articles 9 and 10 |
| Brazil (ANATEL) | Choice of a lab lower in the priority order | 7 working days | A lab that does not quote, or cannot start, within 7 working days may be passed over | Ato 4091/2020, item 5.4 |
| Argentina (ENACOM) | Homologation | Immediate | Once the file with the Certificate of Conformity is complete; regime applies from September 1, 2026 | Res. 57/2026, Annex I |
| Colombia (CRC) | Mobile terminal homologation | 15 working days | CRC answer time; free of charge | CRC FAQ, revision 14 |
| Peru (MTC) | Homologation | 30 working days at most | From the VUCE request | DS 001-2006-MTC Art. 13, as amended by DS 019-2019-MTC |
| Thailand (NBTC) | SDoC | 3 days | Processing time stated by the Office of the NBTC; none stated for Class A or Class B | NBTC presentation, November 2025 |
Every row assumes a complete, correct file. A file returned for correction usually restarts or suspends the clock, so the practical lever is file quality, not the regulatory duration itself.
What no text fixes
Section titled “What no text fixes”These are the steps that decide the real schedule, and no regulator or scheme owner publishes a figure for them:
- Lab queue and test campaign. No regulation sets how long an EMC, LVD or radio test campaign takes. Ask each lab for a dated slot and a report delivery date in the quote.
- Retests after a failure. No published, sourced first-pass failure rate exists for EMC or radio testing; the previous version of this page quoted one without a source and it has been removed.
- TCB review. The FCC rules let each TCB set its own fees and do not set a review time. Only PAG items carry the FCC "2 to 6 weeks" description.
- Notified body examination under the RED. Needed when harmonised standards are not applied in full for Article 3(2) or 3(3) (RED Article 17), including the restricted parts of EN 18031 for 3(3)(d)(e)(f) since August 1, 2025. The body quotes its own timing.
- PTCRB overall. ptcrb.com says certification time depends on the device type and on whether results from related devices can be leveraged; the only fixed clocks are in the table above.
- Verizon and other operators not listed here. Their process documents were not used for this page; ask the operator.
Dated changes that moved a clock (2025 to 2026)
Section titled “Dated changes that moved a clock (2025 to 2026)”| Date | Change | Source |
|---|---|---|
| June 2025 | ISED service standards updated; wireless equipment certification remains 14 calendar days | ISED service standards |
| August 1, 2025 | RED Article 3(3)(d)(e)(f) applies, RED 3.3 cybersecurity becomes part of the conformity assessment | Delegated Regulation (EU) 2022/30 |
| June 15, 2026 | FCC PAG list prioritizes equipment tested in Trusted Test Labs | 47 CFR 2.964(a), FCC 26-28 |
| July 24, 2026 | RRA Notice 2026-4 in force, Article 29 processing times | RRA Notice 2026-4 |
| September 1, 2026 | ENACOM certification-agency regime applies in Argentina, homologation granted once the file is complete | Res. 57/2026 |
| September 11, 2026 | CRA reporting obligations (24 hours, 72 hours, 14 days) apply | CRA Article 71 |
| October 2026 | PTCRB PPMD V4.2 and NAPRD03 V6.26 published | PTCRB |
Planning with these clocks
Section titled “Planning with these clocks”- Sequence by file readiness, not by authority. Every administrative clock above starts at a complete file. Lock the documentation (test reports, user manual, labels) before the first filing.
- Request the PTCRB TAC late enough. The 120-day reservation runs from the request; a TAC requested before testing is booked can lapse.
- Watch the NAPRD03 version. With four releases a year and only the latest two accepted at upload, a slipping campaign can force a retest against a newer version.
- Keep the FCC 30-day set-aside window in mind before shipping volume on a fresh grant (2.962(f)).
- Keep ISED test reports fresh. A report older than 12 months at application is not accepted (RSS-Gen 3.4.1).
- Choose SDoC or certification by the rules, not by speed. Part 15 intentional radiators such as BLE or Wi-Fi transmitters must be certified by a TCB before marketing, unless exempted (47 CFR 15.201(b)); SDoC is not an option for them.
- Get dated quotes from labs, the TCB and any notified body, and put them in the schedule as the only source for the steps no text fixes.
See also the FCC procedure, the RED procedure, the CE procedure, CE tests and the PTCRB procedure.
Claims the texts contradict
Section titled “Claims the texts contradict”| Claim (including the previous version of this page) | What the texts say |
|---|---|
| "A TCB takes 2 to 6 weeks to review an FCC application" | No FCC rule sets a TCB review time. The "2 to 6 weeks" figure in FCC 26-28 describes PAG review only |
| "A complete 4G module takes 6 to 9 months of PTCRB, 5G 8 to 12 months" | No PTCRB or CTIA Certification document gives a duration. The fixed clocks are the 120-day TAC reservation and the NAPRD03 version window (PPMD 8.6, 11.7) |
| "PVG validation comes before TAC/IMEI allocation" and "the PVG meets bi-monthly" | The TAC is requested at the start, from certify.ptcrb.com, and reserved for 120 days (PPMD 8.6). CTIA Certification reviews requests; the PVG is a technical group that validates test cases |
| "30 to 40 percent of products fail EMC on the first campaign" | No source was given and none was found; removed |
| "In 2026 radio lab queues run 4 to 8 weeks, up to 12 for 5G OTA" | No published source; lab queues vary by lab and must come from a dated quote |
| "Add 30 to 50 percent margin to the best case" | No source; removed |
| "Carrier homologations add 4 to 12 weeks each" | T-Mobile states "as little as five business days" under conditions; AT&T states 8 to 12 weeks of PTCRB testing and 4 to 6 weeks of AT&T testing for a device on an unapproved module, while a device built on an AT&T approved module follows a three-step process at no AT&T certification cost |
| "eSIM agreements take 2 to 6 months" | No source. AT&T states approximately 8 weeks for a new eUICC approval under ASAP |
| "Module B+C adds 6 to 16 weeks under the RED" | Neither the RED nor Decision 768/2008/EC sets a duration for EU-type examination |
| "A C2PC takes 2 to 6 weeks" | No FCC rule sets a duration for a Class II permissive change |
| "An MRA lab saves 30 to 40 percent of cost" | No source; removed. Mutual recognition lets one recognised lab test for several regulators, the saving depends on the quotes |
| "Korea, China or Peru take weeks to issue a certificate" | The texts set 5 days (Korea, certification), 15 working days (China, after acceptance, testing excluded) and 30 working days (Peru) |
Sources & references
- 47 CFR Part 2, Subpart J: Equipment Authorization Procedures (eCFR, 2.926, 2.962, 2.964), FCC (eCFR) www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-2/subpart-J
- 47 CFR 15.201, Equipment authorization requirement for intentional radiators (eCFR), FCC (eCFR) www.ecfr.gov/current/title-47/chapter-I/subchapter-A/part-15/subpart-C/section-15.201
- FCC 26-28, Second Report and Order (adopted April 30, 2026), para. 65 on PAG review times, FCC docs.fcc.gov/public/attachments/FCC-26-28A1.pdf
- FCC 26-28 final rule, 91 FR 27843 (May 15, 2026), effective June 15, 2026 except delayed paragraphs, Federal Register www.federalregister.gov/documents/2026/05/15/2026-09822/promoting-the-integrity-and-security-of-telecommunications-certification-bodies-measurement
- OET Knowledge Database (KDB 388624 PAG, KDB 726920 confidentiality), FCC apps.fcc.gov/oetcf/kdb/index.cfm
- Decision No 768/2008/EC, common framework for the marketing of products (Article R23), EUR-Lex eur-lex.europa.eu/eli/dec/2008/768/oj
- Directive 2014/53/EU (RED), Articles 10 and 17, Annexes II to IV, EUR-Lex eur-lex.europa.eu/eli/dir/2014/53/oj
- Delegated Regulation (EU) 2022/30, RED Article 3(3)(d)(e)(f), EUR-Lex eur-lex.europa.eu/eli/reg_del/2022/30/oj
- Regulation (EU) 2024/2847 (Cyber Resilience Act), Articles 14 and 71, EUR-Lex eur-lex.europa.eu/eli/reg/2024/2847/oj
- Regulation (EU) 2017/745 (MDR), Article 42, EUR-Lex eur-lex.europa.eu/eli/reg/2017/745/oj
- ISED, Spectrum and Telecommunications Service Standards (updated June 2025), ISED Canada ised-isde.canada.ca/site/spectrum-management-telecommunications/en/learn-more/key-documents/spectrum-and-telecommunications-service-standards
- RSS-Gen, General Requirements for Compliance of Radio Apparatus (section 3.4.1), ISED Canada ised-isde.canada.ca/site/spectrum-management-telecommunications/en/devices-and-equipment/radio-equipment-standards/radio-standards-specifications-rss/rss-gen-general-requirements-compliance-radio-apparatus
- PTCRB Program Management Document (PPMD) V4.2, October 2026, PTCRB www.ptcrb.com/wp-content/uploads/2026/10/PTCRB-PPMD-V4.2.pdf
- PTCRB Certification Program, PTCRB www.ptcrb.com/
- AT&T, Get Certified (Get Network Ready programme), AT&T iotdevices.att.com/wp/get-certified.aspx
- AT&T, SIM and eSIM (ASAP eUICC approval), AT&T iotdevices.att.com/wp/sim.aspx
- T-Mobile, Start Your IoT Certification (process and FAQ), T-Mobile www.t-mobile.com/business/solutions/iot/device-certification/process
- RRA Notice 2026-4 on Conformity Assessment of Broadcasting and Communications Equipment (Article 29), National Radio Research Agency (Korea) www.law.go.kr/%ED%96%89%EC%A0%95%EA%B7%9C%EC%B9%99/%EB%B0%A9%EC%86%A1%ED%86%B5%EC%8B%A0%EA%B8%B0%EC%9E%90%EC%9E%AC%EB%93%B1%EC%9D%98%EC%A0%81%ED%95%A9%EC%84%B1%ED%8F%89%EA%B0%80%EC%97%90%EA%B4%80%ED%95%9C%EA%B3%A0%EC%8B%9C
- MIIT Order 57, Radio Transmitting Equipment Management Provisions, in force July 1, 2023, State Council Gazette (China) www.gov.cn/gongbao/content/2023/content_5745288.htm
- ANATEL Ato 4091/2020, selection, assessment and habilitation of test laboratories, ANATEL informacoes.anatel.gov.br/legislacao/atos-de-certificacao-de-produtos/2020/1452-ato-4091
- ENACOM Resolución 57/2026, RAMATEL regulation (Boletín Oficial, February 26, 2026), Boletín Oficial (Argentina) www.boletinoficial.gob.ar/detalleAviso/primera/338750/20260226
- CRC, mobile terminal homologation FAQ (revision 14), CRC (Colombia) tramitescrcom.gov.co/Documents/PreguntasFrecuentesHomologacionVF.pdf
- Decreto Supremo 019-2019-MTC, amending the homologation regulation DS 001-2006-MTC, MTC (Peru) portal.mtc.gob.pe/comunicaciones/control_supervision/homologacion_equipos/documentos/DS%20019-2019%20modifica%20DS%20001-2006%20Reglamento%20Homologaci%C3%B3n.pdf
- Overview of NBTC Standards and Conformity Assessment, Office of the NBTC, November 11, 2025 (IEEE 802.18-25/0113r0), Office of the NBTC (Thailand) mentor.ieee.org/802.18/dcn/25/18-25-0113-00-0000-overview-of-nbtc-standards-and-conformity-assessment.pdf
Frequently asked questions
- How long does it take to certify a connected product?
- No regulation sets an end-to-end duration. The texts fix a few administrative clocks: ISED aims to assess a complete wireless certification application within 14 calendar days, Korea issues a certification within 5 days of filing, China decides SRRC type approval within 15 working days of acceptance, Colombia (CRC) answers within 15 working days and Peru (MTC) within 30 working days. Testing, sample logistics and lab queues sit outside all of these clocks and depend on your lab quotes.
- How long does a TCB take to grant an FCC ID?
- No FCC rule sets a TCB review time. The fixed clocks around the grant are the 30 days to pay and validate the Grantee Code fee (47 CFR 2.926(c)) and the 30 days after the grant during which the TCB or the FCC may set it aside (2.962(f)). For equipment on the Pre-approval Guidance list, the FCC wrote in FCC 26-28 that PAG review "typically takes 2 to 6 weeks".
- Does the EU set a deadline for a notified body?
- No. Directive 2014/53/EU (RED) and Decision 768/2008/EC set no time limit for an EU-type examination. The time limits they do set concern other things: the 10-year retention of the technical documentation and the EU declaration of conformity, and the two-week or two-month objection window before a newly notified body may act (Article R23(5)).
- How long does PTCRB certification take?
- No PTCRB or CTIA Certification document gives a duration. The fixed rules are that an IMEI TAC is reserved for 120 days and revoked if the device is not certified by then (PPMD 8.6), and that certification uses the latest NAPRD03 version at report upload or the one before it (PPMD 11.7), with four releases a year. AT&T, for a device on an unapproved module, says PTCRB testing "can take 8-12 weeks".
- How long do carrier approvals take in the United States?
- Only what the carriers publish. T-Mobile says Technical Acceptance can come "in as little as five business days" if all requirements are met with no certification issues. AT&T says that with an unapproved module, PTCRB testing can take 8 to 12 weeks and AT&T lab and field testing 4 to 6 weeks, and that a new eUICC approval under ASAP takes about 8 weeks.