- All guides
- IEC 61000-4-8 magnetic field immunity: 1 to 100 A/m
IEC 61000-4-8 magnetic field immunity: 1 to 100 A/m
The IEC 61000-4-8 test checks immunity to the 50/60 Hz magnetic field with a calibrated induction coil: five severity levels from 1 to 100 A/m (plus an open level X), short-duration fields of 300 and 1 000 A/m at the two highest levels, and three orthogonal axes. The field produced by transformers, motors, distribution cabinets and high-current chargers penetrates enclosures and couples into PCBs. Product standards such as EN 55035 (multimedia), the generic EN 61000-6-1 and 6-2, and IEC 60601-1-2 (medical, 30 A/m for equipment with magnetically sensitive parts) reference this test and set the level and the performance criterion. This page lays out the standards framework (Edition 2.0 of 2009), the severity levels, the geometry of induction coils, the test procedure on the three orthogonal axes, the performance criterion, the connection to IEC 61000-4-9 (pulsed field) and 4-10 (damped oscillatory field), and the campaign pitfalls.
TL;DR:
- Five severity levels for the continuous field: 1, 3, 10, 30 and 100 A/m, plus an open level X; a short-duration field of 1 to 3 s adds 300 A/m at level 4 and 1 000 A/m at level 5.
- Three orthogonal orientations are mandatory, by rotating the EUT 90 degrees or by switching the coil orientation.
- The performance criterion comes from the product standard: product standards generally ask criterion A for the continuous field.
- IEC 60601-1-2 asks 30 A/m for medical equipment with magnetically sensitive parts, in every environment; its 2020 amendment also added proximity magnetic fields per IEC 61000-4-39.
Why a low-frequency magnetic immunity test
Section titled “Why a low-frequency magnetic immunity test”Electromagnetic compatibility splits phenomena into three families: high-frequency fields and currents (radiated and conducted tests above 150 kHz), fast transients (ESD, EFT, surge), and low-frequency fields close to mains. The last family is covered by IEC 61000-4-8 and its neighbours 4-9 and 4-10.
The magnetic field at 50 or 60 Hz is present wherever a significant alternating current flows: a distribution transformer cell typically generates 5 to 50 A/m at one metre, a 10 kW motor produces 1 to 5 A/m at the same distance, an automation cabinet with busbar reaches 10 to 30 A/m at 0.5 metre. These levels correspond to the real environment of industrial or medical equipment installed near electrical infrastructure.
Why a low-frequency field disturbs electronics
Section titled “Why a low-frequency field disturbs electronics”At 50 Hz the wavelength is 6000 km. No antenna or resonant-cavity coupling is at play. The coupling mechanisms are quasi-static. The field penetrates metallic enclosures through apertures (vents, ventilation slots, discontinuous gaskets), because the skin depth in mild steel at 50 Hz is roughly 0.8 mm: a 1 mm sheet attenuates by only a few decibels.
Once inside, the field couples into PCB current loops. A 10 cm square loop exposed to 10 A/m at 50 Hz picks up roughly 50 microvolts peak, which sounds modest but is enough to disturb a 24-bit measurement sensor, a class AB audio amplifier, a Hall sensor or a sensitive relay. Legacy CRT displays were the first victims (beam deflection visible at 1 A/m), but the topic stays current for electron microscopes, precision balances, biomedical signal amplifiers and resistive current sensors.
Standards framework: IEC 61000-4-8 Ed 2.0:2009
Section titled “Standards framework: IEC 61000-4-8 Ed 2.0:2009”The edition in force is IEC 61000-4-8 Ed 2.0:2009, superseding Edition 1.0 of 1993 and its 2000 amendment. Its scope is immunity to magnetic disturbances at the power frequencies of 50 Hz and 60 Hz; it defines the recommended test levels, the test equipment and setup, and the procedure, and leaves the choice of level and performance criterion to product committees.
Product standards that reference IEC 61000-4-8
Section titled “Product standards that reference IEC 61000-4-8”| Product standard | Required level | Criterion | Justification |
|---|---|---|---|
| EN 55035 (multimedia) | Set in its enclosure-port table | Per the standard | Applies only to equipment containing devices susceptible to magnetic fields |
| EN 55024 (IT equipment, legacy pre-CISPR 35) | 1 A/m | A | Office IT equipment |
| EN 61000-6-1 (generic residential) | 3 A/m | A | Generic residential/commercial standard |
| EN 61000-6-2 (generic industrial) | 30 A/m | A | Severe industrial environment |
| EN 60601-1-2 (medical, 4th edition with AMD1:2020) | 30 A/m at 50 or 60 Hz, one value for both healthcare environments | Per the standard | Applies to equipment with magnetically sensitive components or circuitry; raised from 3 A/m in the 3rd edition |
| EN 50121-4 (railway signalling and telecom apparatus) | Per the standard, including the 16.7 Hz traction frequency where relevant | Per the standard | Railway environment |
IEC 60601-1-2 is the case most often misquoted. Its 4th edition raised the power-frequency level from 3 to 30 A/m, and the 2020 amendment (AMD1) restates the row in the enclosure-port table as a single "30 A/m, 50 Hz or 60 Hz" for equipment with magnetically sensitive components or circuitry, with no lower value for home healthcare. The same amendment added a second magnetic test, proximity magnetic fields to IEC 61000-4-39, aimed at sources such as RFID readers and wireless chargers:
| Proximity test frequency (IEC 60601-1-2, Table 11) | Modulation | Immunity test level |
|---|---|---|
| 30 kHz | CW | 8 A/m |
| 134.2 kHz | Pulse modulation, 2.1 kHz | 65 A/m |
| 13.56 MHz | Pulse modulation, 50 kHz | 7.5 A/m |
The 30 kHz test applies only to equipment intended for the home healthcare environment, and, as with power-frequency fields, the test targets equipment with magnetically sensitive components or circuitry; the location of the applied field is set in the test plan and recorded in the report.
Frequencies covered
Section titled “Frequencies covered”The scope of IEC 61000-4-8 is the power frequencies of 50 Hz and 60 Hz: 50 Hz in Europe and most of the world, 60 Hz in North America and parts of Japan. Other frequencies come from product or sector standards, not from IEC 61000-4-8 itself:
- 16.7 Hz for the 15 kV traction networks of Germany, Austria, Switzerland, Sweden and Norway, where railway standards call for it.
- 400 Hz for aircraft and some military equipment, under their own environmental test standards.
See the glossary for the EMC acronyms, and CE tests for the general EMC framework in the EU.
What are the IEC 61000-4-8 test levels?
Section titled “What are the IEC 61000-4-8 test levels?”The standard defines five severity levels. The applicable level is set by the product standard.
| Level | Continuous field intensity | Short-duration intensity | Typical environment |
|---|---|---|---|
| 1 | 1 A/m | - | Residential far from industrial sources |
| 2 | 3 A/m | - | Typical residential and commercial |
| 3 | 10 A/m | - | Moderate industrial |
| 4 | 30 A/m | 300 A/m (1 to 3 s) | Severe industrial, medical critical care |
| 5 | 100 A/m | 1 000 A/m (1 to 3 s) | Heavy industrial, close to high-current busbars |
| X | Specified by product standard | Specified | Special case |
The short-duration level (column 3) applies in addition to the continuous field at levels 4 and 5 only, and simulates transient phenomena associated with a short-circuit or a motor start. It runs for 1 to 3 seconds, or in a variant 1 to 10 cycles of the mains frequency (20 to 200 ms at 50 Hz).
Quick read for the designer
Section titled “Quick read for the designer”For a consumer product certified to EN 55035, the requirement is typically 1 A/m: a permissive level, reachable without special precautions. For an industrial product certified to EN 61000-6-2, the requirement rises to 30 A/m: this calls for magnetic shielding considerations, orientation of sensitive loops, and filtering on analogue sensors. For a medical device intended for critical care (EN 60601-1-2 in a professional healthcare environment), 30 A/m is mandatory and requires a robust architecture from the PCB upward.
Test hardware and configuration
Section titled “Test hardware and configuration”An IEC 61000-4-8 campaign relies on a high-power mains-frequency generator, a calibrated induction coil and an EUT-positioning system.
The generator
Section titled “The generator”The generator supplies alternating current at the test frequency (50 or 60 Hz, or another frequency where the product standard asks for it). To produce 30 A/m at the centre of a 1 m by 1 m coil, typically 24 to 30 A are needed in a single-turn coil. Frequency stability and harmonic content are controlled: THD below 8 percent is required by the standard. The reference manufacturers are EM TEST (MIG 5060 and MIG OS6), Teseq/Ametek (ECOS and NSG 1007).
The induction coil
Section titled “The induction coil”Three geometries are specified:
- Single square coil 1 m by 1 m, single thick-section turn on a non-magnetic frame. Typical calibration constant: 0.87 A/m per ampere injected at centre.
- Single rectangular coil 1 m by 2.6 m, for larger EUTs. Different constant, supplied by the manufacturer.
- Two-element Helmholtz coils, two parallel coils separated by their radius, producing a very uniform field in the central volume. More accurate but bulkier.
The coil holds an annual calibration certificate giving the field map inside its usable volume (typically the central 50 percent of the bounding volume), with the uniformity tolerance per the standard (plus or minus 3 dB).
Configuration diagram
Section titled “Configuration diagram” +-------------------------------+ | Induction coil (1 turn) | | geometry 1 m x 1 m | | | | +-------------------+ | | | | | | | EUT energised | | | | centred in the | | | | uniform volume | | | | | | | +-------------------+ | | | | | | 90 deg rotations | | | X, Y, Z | | v | +-------------------------------+ | | | | +------------+ | | Generator | | | 50/60 Hz | | | I = 0 to 30A| | +------------+ | | | +--- GRP ---+ | Earth
Orientations to test (3 orthogonal axes): X horizontal Y horizontal Z vertical [EUT] [EUT rotated 90 deg] [EUT rotated 90 deg]Ambient conditions and EUT setup
Section titled “Ambient conditions and EUT setup”The EUT sits on a non-conductive wooden table or non-magnetic support, centred in the uniform volume of the coil. The test room must be away from ambient-field sources above 1 A/m, which excludes immediate proximity to HV-to-LV transformers or unshielded distribution panels. The report logs the ambient field before and after the test.
The EUT runs its typical application software during the test (simulated ECG trace, sensor bus traffic, network packet stream). The observation setup must detect any degradation, even brief.
How is the test performed? The three orthogonal axes
Section titled “How is the test performed? The three orthogonal axes”The test consists of applying the field at the specified intensity in the three orthogonal orientations in turn, observing the EUT during and after each sequence.
Standard sequence for a continuous level
Section titled “Standard sequence for a continuous level”For a level 4 test (30 A/m) the procedure is:
- EUT stabilisation. The EUT is energised, its application software runs, and the observation is verified as nominal for at least 1 minute.
- Orientation 1 (X horizontal). The field is established at 30 A/m, held for 1 to 3 seconds after stabilisation, then cut. The observation is verified during and after.
- 90 degree rotation. The EUT is rotated about a vertical axis to expose Y to the field direction.
- Orientation 2 (Y horizontal). The cycle repeats: field established, held, cut, observed.
- 90 degree rotation about a horizontal axis. The EUT is tilted to expose Z (vertical) to the field direction.
- Orientation 3 (Z vertical). The cycle repeats.
A common variant: instead of rotating the EUT, the coil is rotated, or a three-orthogonal-coil system is used and the excitation is switched between them. The physical result is equivalent.
Sequence for the short-duration level
Section titled “Sequence for the short-duration level”When the product standard specifies the short-duration level (levels 3 or 4), a second sequence follows the continuous sequence: the field is applied at the transient amplitude (100 or 300 A/m) for 1 to 3 seconds, or for 1 to 10 cycles of mains frequency (20 to 200 ms at 50 Hz), per the product specification. This mode simulates a nearby short-circuit or a high-power motor start.
Observation and acceptance
Section titled “Observation and acceptance”The observer verifies the EUT's primary function during each application of the field and during the 1 to 3 seconds after the cut. Any degradation, even brief, is logged with the orientation, the level and the nature of the observation (communication loss, measurement artifact, analogue output drift).
Performance criterion: set by the product standard
Section titled “Performance criterion: set by the product standard”As a basic EMC publication, IEC 61000-4-8 does not itself impose a performance criterion: the product standard does. In practice most product standards ask criterion A for the continuous field, and the reason is physical. A power-frequency magnetic field is not a transient in the real environment: equipment installed near a transformer stays exposed for years, so a degradation tolerated in the lab would be a permanent degradation on site.
The short-duration field (300 A/m at level 4, 1 000 A/m at level 5, for 1 to 3 seconds) represents fault conditions such as a short-circuit current, and product standards that use it may accept a different criterion for it. Read the criterion in the product standard you test against rather than assuming one.
The magnetic family: 4-8 vs 4-9 vs 4-10
Section titled “The magnetic family: 4-8 vs 4-9 vs 4-10”Three IEC 61000-4-x tests cover magnetic phenomena. Their relationship is summarised below.
| Test | Simulated phenomenon | Levels | Duration | Criterion | Typical product standard |
|---|---|---|---|---|---|
| IEC 61000-4-8 | Continuous power-frequency magnetic field (50/60 Hz) | 1 to 100 A/m continuous; 300 and 1 000 A/m short-duration | Continuous, 1 to 3 s | Per product standard, usually A | EN 55035, IEC 60601-1-2, EN 61000-6-2 |
| IEC 61000-4-9 | Pulsed magnetic field (nearby lightning strike, short-circuit) | 100 to 1000 A/m peak | 6.4/16 microsecond pulse | B | EN 61000-6-5 (substations), EN 61000-6-2 |
| IEC 61000-4-10 | Damped oscillatory magnetic field (HV switching) | 10 to 100 A/m peak | 100 kHz or 1 MHz oscillation | B | EN 61000-6-5, severe industrial EN 61000-6-2 |
IEC 61000-4-9, pulsed field
Section titled “IEC 61000-4-9, pulsed field”The 4-9 test simulates the magnetic effect of a very high fault current (distribution short-circuit, nearby lightning). The pulse has a 6.4 microsecond front and 16 microsecond half-duration, with peaks up to 1000 A/m at level 5. Criterion B applies, the phenomenon being transient. Mainly relevant for HV substations and severe industrial environments.
IEC 61000-4-10, damped oscillatory field
Section titled “IEC 61000-4-10, damped oscillatory field”The 4-10 test simulates HV breaker or disconnector switching, which generates a damped oscillation at 100 kHz or 1 MHz. Peak 100 A/m at level 5. Criterion B applies. Mainly relevant for substation equipment.
For neighbouring EMC tests, see ESD per IEC 61000-4-2, surge and burst per IEC 61000-4-5 and 4-4, and mains dips and interruptions per IEC 61000-4-11.
The medical case: 30 A/m in IEC 60601-1-2
Section titled “The medical case: 30 A/m in IEC 60601-1-2”IEC 60601-1-2 is the product standard most often misquoted on this test. Its 4th edition raised the power-frequency level from 3 to 30 A/m, and Amendment 1 of 2020 restates the row of the enclosure-port table (Table 4) as a single value: 30 A/m at 50 Hz or 60 Hz, applicable to medical electrical equipment with magnetically sensitive components or circuitry. There is no lower value for the home healthcare environment, and no separate ICU or operating-room level.
The performance criterion for each function comes from the manufacturer's risk management: if loss of a function under the field could harm the patient, that function has to keep working. The justification belongs in the risk-management file and in the test report.
The same amendment added proximity magnetic fields to IEC 61000-4-39; see the table in the product-standards section above.
See also
Section titled “See also”- ESD per IEC 61000-4-2: method and test levels
- Surge and Burst (IEC 61000-4-5 / 4-4): EMC transients
- Voltage dips + interruptions (IEC 61000-4-11)
- Harmonics and flicker (IEC 61000-3-2 and 3-3): mains quality
Common campaign pitfalls
Section titled “Common campaign pitfalls”Six errors recur in first-pass failure reports for the 4-8 test.
-
EUT positioned outside the uniform volume. The coil produces a uniform field in only the central 50 percent of its bounding volume, with a plus or minus 3 dB tolerance. An EUT placed near the coil edge receives a weaker field than expected, and the lab may wrongly conclude the EUT is compliant. The test plan must specify positioning and the report must photograph it.
-
One of the three orientations omitted. The classic pitfall on flat-lay EUTs is to forget the vertical axis, which requires a rotation about a horizontal axis that is not always practical. Testing X and Y without Z passes an EUT that would have failed on Z. The report must photograph all three rotations.
-
Coil calibration out of date. The coil's A/m-per-ampere constant drifts if the frame deforms, if the turn is displaced, or if a magnetic mass has been added nearby. Annual calibration is mandatory, and absence of ferromagnetic mass within 2 metres is documented.
-
EUT in standby or out of nominal mode. Equipment tested in standby exercises few sensitive functions and often passes trivially. The test plan must specify the operating mode (measurement loop, simulated ECG capture, active network transmission) and the observation criterion.
-
High generator THD. A generator with THD above 8 percent injects harmonics that couple differently than pure 50 Hz. The standard requires THD below 8 percent at rated current; the measurement is logged in the report.
-
Ambient field not measured. The test room must have an ambient field below 1 A/m. A room near an unshielded distribution transformer can exceed that. Measuring the ambient field before and after the test is mandatory. See CE pitfalls for general EMC reporting anomalies.
Robust design for low-frequency magnetic fields
Section titled “Robust design for low-frequency magnetic fields”Compliance with 4-8, especially at the 30 A/m level, is decided upstream by PCB and enclosure design.
Reduce sensitive current loops
Section titled “Reduce sensitive current loops”Any closed current loop on a PCB picks up an electromotive force proportional to the area, the field intensity, and the frequency. At 50 Hz and 30 A/m, a 100 square cm loop picks up roughly 170 microvolts peak. Reducing the loop area (signal return routed close to the forward path, continuous ground plane) reduces the induced parasitic voltage proportionally.
Orientation of sensitive components
Section titled “Orientation of sensitive components”Components with a strong magnetic coupling factor (relay coils, measurement transformers, Hall sensors, moving-coil microphones) have a sensitive direction. Orienting them so their sensitive axis is perpendicular to the most likely orientation of the external field reduces coupling. This optimisation targets a specific axis, but the three-orthogonal-axes test verifies that the EUT survives in any orientation.
Magnetic shielding
Section titled “Magnetic shielding”Mild-steel enclosures attenuate poorly at 50 Hz (0.8 mm skin depth, a few dB per millimetre). For significant shielding, high-permeability materials are needed: mumetal, permalloy, low-frequency ferrites. A 0.5 mm mumetal shield can reach 30 to 40 dB attenuation at 50 Hz, but the material is expensive, fragile, and loses its properties after bending if not annealed. A full mumetal envelope is typically reserved for very-high-precision instruments.
Filtering and software integration
Section titled “Filtering and software integration”On analogue sensors, a low-pass filter with cutoff below 50 Hz attenuates the induced parasitic. On ECG or audio measurements, a 50 Hz notch is standard. In software, averaging over 20 or 40 ms windows (one or two mains periods) removes the residual magnetic component.
What to remember
Section titled “What to remember”- IEC 61000-4-8 Ed 2.0:2009 evaluates immunity to a continuous magnetic field at the power frequencies of 50 and 60 Hz.
- Five severity levels: 1, 3, 10, 30 and 100 A/m, plus an open level X. A short-duration field of 1 to 3 seconds adds 300 A/m at level 4 and 1 000 A/m at level 5.
- Three orthogonal orientations mandatory, by EUT rotation or by orthogonal-coil switching.
- The criterion comes from the product standard; most ask criterion A for the continuous field, because the phenomenon is permanent in the real world.
- IEC 60601-1-2 asks 30 A/m at 50 or 60 Hz for medical equipment with magnetically sensitive parts, with one value for professional and home healthcare, and adds proximity magnetic fields per IEC 61000-4-39 since 2020.
- IEC 61000-4-9 and 4-10 complete the magnetic family: 4-9 pulsed (lightning, short-circuit), 4-10 damped oscillatory (HV switching). Both accept criterion B.
- Robustness comes from design: smaller sensitive current loops, oriented relay coils and Hall sensors, mumetal shielding for extreme cases, low-pass and 50 Hz notch filtering on sensitive sensors.
For practical certification, see CE tests for the EU EMC framework, RED tests for radio, and the glossary.
Sources & references
- IEC 60601-1-2:2014/AMD1:2020, Table 4 and Table 11 (public sample), IEC via iTeh Standards cdn.standards.iteh.ai/samples/100132/e7d4039bdb1f4559aa3c012ff789f5b6/IEC-60601-1-2-2014-AMD1-2020.pdf
- IEC 61000-4-8 Ed 2.0:2009, power-frequency magnetic field immunity test, IEC webstore.iec.ch/publication/4229
- EN 60601-1-2:2015+A1:2021, medical devices, electromagnetic compatibility, IEC webstore.iec.ch/en/iec-search/result?q=EN%2060601-1-2
- EN 55035:2017+A11:2020, multimedia equipment, electromagnetic immunity, CENELEC standards.cencenelec.eu/dyn/www/f?p=205:110:0::::FSP_PROJECT,FSP_ORG_ID:67027,1258635
- EN 55024:2010+A1:2015, information technology equipment, immunity, CENELEC standards.cencenelec.eu/dyn/www/f?p=205:110:0::::FSP_PROJECT,FSP_ORG_ID:35375,25
- IEC 61000-4-9, pulsed magnetic field immunity test, IEC webstore.iec.ch/publication/4231
- Directive 2014/30/EU on electromagnetic compatibility, EUR-Lex eur-lex.europa.eu/eli/dir/2014/30/oj
Frequently asked questions
- Why test equipment against a 50 Hz magnetic field?
- Power transformers, asynchronous motors, distribution switchgear and high-current chargers continuously generate magnetic fields at the mains frequency (50 Hz in Europe, 60 Hz in North America). Those fields penetrate metallic enclosures through apertures and cabling, and couple into PCB current loops. A poorly shielded Hall sensor, a relay coil, a legacy CRT display or a sensitive audio amplifier can be disturbed. IEC 61000-4-8 verifies that the equipment maintains its function under continuous exposure, a typical condition for installations near a transformer substation or an electrical cabinet.
- How does IEC 61000-4-8 differ from 4-9 and 4-10?
- IEC 61000-4-8 covers continuous power-frequency magnetic field at 50 or 60 Hz; product standards may call for other frequencies, such as the 16.7 Hz of some railway traction networks. IEC 61000-4-9 covers pulsed magnetic field, simulating the effect of a short-circuit current or a nearby lightning strike: 6.4/16 microsecond pulse, levels up to 1000 A/m peak. IEC 61000-4-10 covers damped oscillatory magnetic field, simulating high-voltage breaker and switch operations: 100 kHz or 1 MHz oscillation, levels up to 100 A/m. The three tests are complementary and all three appear in EN 61000-6-2 for the severe industrial environment.
- Which level applies to which environment?
- Level 1 (1 A/m) corresponds to a residential environment far from industrial sources. Level 2 (3 A/m) covers typical residential and commercial. Level 3 (10 A/m) is the common requirement for industrial and tertiary buildings, with moderate power-equipment presence. Level 4 (30 A/m) targets the severe industrial environment near transformers or high-current chargers, and level 5 (100 A/m) heavy industrial sites close to high-current busbars. In medical equipment, IEC 60601-1-2 (4th edition, as amended in 2020) sets a single 30 A/m at 50 Hz or 60 Hz in its enclosure-port table, applicable to equipment with magnetically sensitive components or circuitry, without distinguishing the professional and home healthcare environments.
- Continuous field or short-duration field, which procedure?
- The standard distinguishes two modes by phenomenon type. The continuous field is applied for at least 1 to 3 seconds after stabilisation, long enough to observe steady-state EUT behaviour; this is the case for the generic levels 1 to 4. The short-duration field (transient test) applies the level for 1 to 10 cycles of the mains frequency, i.e. 20 ms to 200 ms at 50 Hz; this mode simulates short-circuit phenomena or motor inrush. The product standard specifies which of the two modes applies, and some require both in sequence.
- Why test on three orthogonal axes?
- A magnetic field has a direction in space. The sensitive structures inside the EUT (PCB current loops, relay coils, Hall sensors) respond to the field according to their own orientation. Testing a single axis leaves the other two orientations untested, and a product can pass on X yet fail on Y or Z. The standard therefore requires three orthogonal orientations, obtained by rotating the EUT 90 degrees after each sequence (or by switching the coil orientation, which is equivalent). The report documents all three orientations and the observed behaviour for each.
- Which performance criterion applies?
- The product standard sets it: IEC 61000-4-8 is a basic EMC publication and leaves the criterion to product committees. Most product standards ask criterion A for the continuous field, because the phenomenon (power-frequency field) is permanent in the real world: a degradation that clears at the end of a lab test would be a lasting loss of function on site. The argument is physical: in the real environment the field does not disappear, so any temporary failure becomes a permanent failure on site.
- How is the induction coil sized?
- The standard describes two accepted geometries: the 1 metre square single coil and the double Helmholtz coil, which produces a more uniform field in its central volume. For small EUTs the single coil suffices. For larger EUTs, enlarged geometries (1 m by 2.6 m or two-turn coils in series) are specified. The coil manufacturer supplies the calibration constant that ties injected current to the magnetic field produced at centre, in A/m per ampere of excitation. The calibration is verified annually against a traceable field probe.
- Which campaign mistakes drive first-pass failures?
- Three pitfalls recur in failure reports. First, EUT positioning outside the uniform field volume of the coil (typically the central 50 percent): the field there is weaker, the lab applies an apparent level but the EUT does not receive the required level, and post-campaign verification is harsh. Next, omission of one of the three orthogonal orientations, often the vertical axis on flat-lay EUTs: the report must show all three rotations. Finally, EUT in standby instead of active operation: equipment tested outside its nominal regime passes trivially, because no sensitive function is exercised.